Heating Retrofit of a Logistics Centre near the D1 Motorway

An energy audit showed that it was cost-effective to retain the distribution system and replace only the heat sources and controls. Gas consumption dropped by a third.

Scope of Work

The operator of a logistics park wanted to reduce heating costs for the warehouses and administrative section. The original plan was to replace the entire boiler room.

  • Energy audit of the entire site including two solution variants
  • Gas boiler room retrofit — retained distribution system, new condensing heat sources
  • New equalizer control and integration with the building's BMS
  • Hydraulic balancing of the heating system including a balancing report
  • Updated energy performance certificate (PENB) after completion of measures

Outcome

The investment came in approximately 40% lower than the proposed full replacement. After the first season, gas consumption dropped by roughly a third, and the site passed the mandatory inspection of operating systems.

Project Parameters

Location
Central Bohemian Region, Středočeský kraj
Completed
July 2026
Area Served
18 400 m²
Duration
9 měsíců
Category
Energy and Audits, Heating

Technologies Deployed

Condensing boilers Equalizer control Measurement and control with monitoring Hydraulic balancing